Research / Cost drift statistics / Contractors' share of the extra cost of overruns, Belgian public infrastructure (expert survey)
Contractors' share of the extra cost of overruns, Belgian public infrastructure (expert survey)
This figure is outside your filter. Clear the filter.
40.5% of the extra cost of overruns: Contractors' share of the extra cost of overruns, Belgian public infrastructure (expert survey) (Molinari, Haezendonck, Van Rompay, Mabillard & Dooms, 2025; Belgium; low confidence).
What it is. 40.5% of the total additional cost caused by overruns, as apportioned across the parties by 52 surveyed experts.
Sample. 52 Belgian public infrastructure stakeholders, 35% of them general contractors. Public tendering authorities were assigned 49% and contractors 40.5%.
What it is not. An opinion of who pays, not a measured cost: respondents apportioned 100% of the extra cost by judgement. Contractors assigned themselves 50.7%, others assigned them 35.6%. Belgium only, and a share of the overrun, not of the contract, so it is never multiplied by a contract value.
Where it came from
- Molinari, Haezendonck, Van Rompay, Mabillard & Dooms (2025), Persisting Cost Overruns in Public Infrastructure Projects: Lessons From the Belgian Case · free copySection 3.2.3.4 'Distributing the impact occurred due to cost overruns', p.18 of the accepted manuscript; survey question, Section 2.2, p.7 · source record