Research / Cost drift statistics / Contractors' share of the extra cost of overruns, Belgian public infrastructure (expert survey)
Contractors' share of the extra cost of overruns, Belgian public infrastructure (expert survey)
40.5% of the extra cost of overruns: Contractors' share of the extra cost of overruns, Belgian public infrastructure (expert survey) (Molinari, Haezendonck, Van Rompay, Mabillard & Dooms, 2025; Belgium; low confidence).
What it is. 40.5% of the total additional cost caused by overruns, as apportioned across the parties by 52 surveyed experts.
Sample. 52 Belgian public infrastructure stakeholders, 35% of them general contractors. Public tendering authorities were assigned 49% and contractors 40.5%.
What it is not. An opinion of who pays, not a measured cost: respondents apportioned 100% of the extra cost by judgement. Contractors assigned themselves 50.7%, others assigned them 35.6%. Belgium only, and a share of the overrun, not of the contract, so it is never multiplied by a contract value.
Where it came from
- Molinari, Haezendonck, Van Rompay, Mabillard & Dooms (2025), Persisting Cost Overruns in Public Infrastructure Projects: Lessons From the Belgian Case · free copySection 3.2.3.4 'Distributing the impact occurred due to cost overruns', p.18 of the accepted manuscript; survey question, Section 2.2, p.7 · source record