Research / Cost drift statistics / Upward revision of early public cost estimates when scrutinised at budget commitment, Australian transport projects 2001-2015

Upward revision of early public cost estimates when scrutinised at budget commitment, Australian transport projects 2001-2015

25%of the first promised cost
AustraliaTender pricingModerate confidenceOwner's money

25% of the first promised cost: Upward revision of early public cost estimates when scrutinised at budget commitment, Australian transport projects 2001-2015 (Terrill & Danks (Grattan Institute), 2016; Australia; moderate confidence).

What it is. 25% of the first publicly announced cost: the average increase needed once an announcement made before any formal budget commitment was scrutinised in the budget process.

Sample. Australian transport projects completed between 2001 and 2015, from the Investment Monitor database (Grattan Institute 2016). The 25% applies to projects whose first cost was announced before a formal budget commitment, which are 32% of projects and 74% of the value of overruns; after the budget commitment their costs rose by a further 26%. The text does not give the number of projects behind the 25%.

What it is not. An owner's early public estimate, not a contractor's tender price: the client's money, and mostly before any contractor was signed. Grattan describes these as politicians' promised costs made before a budget commitment, and says they "need to be upwardly revised by an average of 25 per cent" once scrutinised: an average of revisions, with no stated sample, not a measured tender shortfall. It covers only announcements made ahead of a budget commitment and is from transport projects of $20m or more, not civil work generally. It is a stated average with no sample size. The report says early announcements are made for electoral reasons, not that the estimates were wrong because contractors priced short. The contractor's side of tender pricing has no national figure here.

Where it came from

Considered and set aside

overrun/tender_estimate_revision_early_announcement_au · AU · F42 ·the record ·link to this figure ·dispute this figure(or email support@demiton.io)