Research / Missed claims statistics / No published Australian figure for delay costs granted in time but not claimed in money
No published Australian figure for delay costs granted in time but not claimed in money
This figure is outside your filter. Clear the filter.
No published Australian figure for delay costs granted in time but not claimed in money: no defensible figure has been published (O'Leary & Vaz-Serra, 2025; Australia; low confidence).
What it is. None - nine Australian sources opened, none measures prolongation, standby or extended-preliminaries money that went unclaimed after time was granted.
Sample. Search terms: extension of time claims liquidated damages Australian construction empirical; delay cost prolongation claims percentage Australia; delay costs recovery survey Australian contractors; unrecovered costs claims per cent of contract value Australia; Australian Constructors Association contract risk survey; Arcadis construction disputes Australia causes. The nearest measure is time-related site overhead: 30 Australian estimators put 45.49% of preliminaries as time-related for the whole job (Table 6), and preliminaries at 10% to 20% of the contract sum (UK 2002, second-hand); the corpus holds the resulting per-day worked example in this cause as weather_wet_day_overhead, and the share-of-contract arithmetic as a `none` record, weather_unclaimed_days_share_of_contract (both moved here from penalty_days on review): calculations, not measurements of money left unclaimed. Not counted because it would not open: HKA Crux 2025 (global, page without figures), Austlii judgments (403).
What it is not. Recorded as `none` on purpose. The time-related overhead share says what a delay day costs in principle, not how many such days go unclaimed once time is granted, which no source we could open measures.
Where it came from
- O'Leary & Vaz-Serra (2025), Challenges in pricing preliminaries costs for contractors: An Australian case studyintroduction citing Chan & Pasquire 2002; table 6 (30 Australian estimators) · source record
Considered and set aside
- Transport for NSW: Clause 43 pays wet-weather delay costs only above a nominated threshold of days, and the guide note sets the rate at 50% of the site-overhead rate: a contract rule from one agency, not a measure of what contractors fail to claim.
- Infrastructure Australia: Says contractor claims are growing and cites delay-driven disputes, with no count or dollar figure for delay costs claimed or missed.
- Hasib & Al-Kilidar (University of Technology Sydney): Ranks causes of delay by perceived importance (28 respondents); measures no cost and no claim outcome.
- Arcadis with the Australian Constructors Association: Costs absorbed after contractual mitigation including extensions of time, but only for market price escalation, with no respondent count and no values printed on the chart.
- Love, Zhou, Edwards, Irani & Sing: 16 rail projects; reports cost increases by scope change and mentions delays only as background, with no delay-cost measure.
- Love, Irani, Smith, Regan & Liu: 67 projects' change orders in total; no extension-of-time or prolongation category.
- Terrill, Coates & Danks (Grattan Institute): 836 transport projects' overruns from announcement, owner-side and not split by cause.
- Department of Infrastructure, Transport, Regional Development, Communications and the Arts: $32.8bn of known cost pressures and delivery delays across the federal pipeline, not split by cause; government money.
- Queensland Parliament, Minister for Transport and Main Roads: Net variations in contract scope, cost or time across Queensland road contracts, with no separation of delay costs; Queensland only.