Research / Missed claims statistics / Client-approved change orders, 67 Australian public infrastructure projects
Client-approved change orders, 67 Australian public infrastructure projects
This figure is outside your filter. Clear the filter.
10.6% of contract value: Client-approved change orders, 67 Australian public infrastructure projects (Love, Irani, Smith, Regan & Liu, 2017; Australia; moderate confidence).
What it is. 10.6% of original contract value, client-approved change orders.
Sample. 67 completed public infrastructure projects from one contractor, Australia, civil, 2011-2014. Change orders totalled about AU$342m against about AU$3.2bn of original contract value, so 10.6% is a total over a total (the paper calls it a mean: average change orders of about AU$5.1m over average contract value of about AU$48.2m).
What it is not. SIZE OF THE POT, NOT A LOSS. No study measures how much of it a typical contractor fails to claim. Change orders were linked to HIGHER contractor margins, which is the opposite of a loss.
Where it came from
- Love, Irani, Smith, Regan & Liu (2017), Cost Performance of Public Infrastructure Projects: The Nemesis and Nirvana of Change-Orders · free copyTable 2; accepted manuscript, Change-Orders section · source record