Research / Missed claims statistics / Client-approved change orders, 67 Australian public infrastructure projects

Client-approved change orders, 67 Australian public infrastructure projects

10.6%of contract value
AustraliaModerate confidenceMoney at stake

10.6% of contract value: Client-approved change orders, 67 Australian public infrastructure projects (Love, Irani, Smith, Regan & Liu, 2017; Australia; moderate confidence).

What it is. 10.6% of original contract value, client-approved change orders.

Sample. 67 completed public infrastructure projects from one contractor, Australia, civil. Mean change orders were about AU$5.1m and made up 11% of work value 2011-2014.

What it is not. SIZE OF THE POT, NOT A LOSS. No study measures how much of it a typical contractor fails to claim. Change orders were linked to HIGHER contractor margins, which is the opposite of a loss.

Where it came from

claim_window/entitlement_variations_pot · AU · F42 ·the record ·link to this figure ·dispute this figure(or email support@demiton.io)