Research / Missed claims statistics / Contract variations as a share of project cost, Queensland public infrastructure (QAO audit)

Contract variations as a share of project cost, Queensland public infrastructure (QAO audit)

9%of construction cost
QLDModerate confidenceMoney at stake

9% of construction cost: Contract variations as a share of project cost, Queensland public infrastructure (QAO audit) (Queensland Audit Office, 2022; QLD; moderate confidence).

What it is. 9% of the cost of the projects examined: over A$127 million in contract variations.

Sample. The Queensland Government infrastructure projects (mostly schools and public buildings) examined in QAO Report 16: 2021-22. One project, Fortitude Valley State Secondary College, reached 21.5% of its original contract value.

What it is not. A handful of audited building projects, not a sample of Queensland civil work. The denominator is total project cost, not the original contract value. Variations are money the client agreed to pay, the size of the pot, not a contractor loss. Corroborates the 10.6% change-order figure (67 Australian projects) from a Queensland regulator.

Where it came from

claim_window/entitlement_variations_qld_public · AU-QLD · F41 ·the record ·link to this figure ·dispute this figure(or email support@demiton.io)