Research / Missed claims statistics / No published New Zealand figure for delay costs (prolongation, standby plant, extended preliminaries) not claimed, as a share of contract value or per day
No published New Zealand figure for delay costs (prolongation, standby plant, extended preliminaries) not claimed, as a share of contract value or per day
This figure is outside your filter. Clear the filter.
No published New Zealand figure for delay costs (prolongation, standby plant, extended preliminaries) not claimed, as a share of contract value or per day: no defensible figure has been published (Building Disputes Tribunal (Te Taraipiunara Tautohe Hanga Whare), 2023; New Zealand; low confidence).
What it is. None - New Zealand sources describe delay and extension of time disputes, but none gives a delay cost per day, a share of contract value, or the share of delay costs left unclaimed.
Sample. Search terms: New Zealand construction delay costs prolongation claims study; extension of time cost claims New Zealand survey; delay and disruption costs per day New Zealand; standby plant delay claim; preliminaries time-related New Zealand; Transmission Gully delay payments; Te Waihanga delay. A frequency exists: the Tribunal lists extensions of time and delay cost claims among the common issues in adjudication but has not collected statistics on types (printed pp.29-30 of its 2023 report). The Tribunal report is the source of record because it is the New Zealand national source that names delay cost claims as a routine adjudication issue and states it holds no figures for them. Reports of a NZ$190.6 million settlement with the Transmission Gully builder were seen in press only and cover one project.
What it is not. Recorded as none on purpose. A count of days is not a cost: no source gives money per delay day. The Australian per-day preliminaries figure in this corpus is Australian and is not carried across. Not read: the Waka Kotahi final account data, NZS 3910 commentary, and Transmission Gully settlement papers.
Where it came from
- Building Disputes Tribunal (Te Taraipiunara Tautohe Hanga Whare) (2023), Tracking the Trends: A report on statutory adjudication in Aotearoa New Zealand 2003-2023'Costs - How much does it cost?', 'Average costs all claims' table, pp.31-32 · source record
Considered and set aside
- Advisian for the New Zealand Treasury Infrastructure Transactions Unit: Reports time bars on variation and extension of time claims, often 10 working days; no delay cost amounts or counts.
- Russell McVeagh: Perception survey: employer variation and design problems are the commonest delay causes and 20% expect delays and extensions of time to cause disputes. Shares of respondents, no money.
- Atapattu, Massey University (PhD thesis): Delays in design rate 79% on a severity index (fourth of 53); contractual claims such as extensions of time with cost claims appear in only 8 articles of the literature review. Ratings and counts of papers, not costs.
- New Zealand Infrastructure Commission / Te Waihanga: Says delays and scope uncertainty raise costs in general terms; no delay cost per day or unclaimed amounts.
- Office of the Auditor-General: National audit of state highway maintenance contracts; reports on no delay claims.
- Mbachu and Taylor: Full text read (36 usable responses, mostly Wellington): ranks contractual risks by mean significance; no delay cost figure.
- Insurance Council of New Zealand: Insured claims from Cyclone Gabrielle (NZ$890 million at March 2023); it does not separate business interruption or contractors' standby costs.
- Adafin, Rotimi and Wilkinson: Cost plan against tender sum drift of 23.86% across 36 commercial projects supplied by the 64 project managers surveyed; pre-award estimating, not prolongation costs.