Research / Rework statistics / No published New Zealand figure for the cost of planning, procurement and sequencing failures
No published New Zealand figure for the cost of planning, procurement and sequencing failures
This figure is outside your filter. Clear the filter.
No published New Zealand figure for the cost of planning, procurement and sequencing failures: no defensible figure has been published (Auckland University of Technology, for BRANZ, 2023; New Zealand; low confidence).
What it is. None: New Zealand sources measure waste by mass or volume and rank planning as a cost factor, and none prices wrong or surplus orders as a share of project cost.
Sample. Search terms: BRANZ construction waste New Zealand over-ordering materials percent; wrong materials ordered rework New Zealand; temporary works failure cost New Zealand; construction procurement supply chain delay cost percent of project New Zealand; Construction Sector Accord procurement. A frequency exists but is not a cost: AUT's scoping study puts construction and demolition waste at about 40% of New Zealand landfill, with estimates of 30% to 50% by source, and names over-ordering of wet concrete as a source of concrete waste (ER82). A BRANZ and EBOSS supplier survey of freight cost and delays turned up in search but was not opened.
What it is not. Recorded as none on purpose: waste by mass, landfill share and contractors' own waste percentages by material (1998 to 1999) are not a cost as a share of project value, and are not filed as one.
Where it came from
- Auckland University of Technology, for BRANZ (2023), Understanding waste generation in the New Zealand construction sector: Scoping study (BRANZ External Research Report ER82)Executive Summary (key issue 1); concrete waste section; supply-chain material · source record
Considered and set aside
- BRANZ (Roman Jaques): Contractors estimate material waste by material (for example plasterboard 5% to 15%) in 1998; 38 Wellington-area respondents, an estimate of quantity wasted, not cost, and dated.
- BRANZ (Roman Jaques): 84 Auckland respondents; non-standard sizing (53%) is the main cause of waste named by contractors; quantities and perceptions, no cost.
- Massey University (Asadi, Wilkinson, Rotimi): Materials and equipment and process causes of rework are among those the standard contract covers; clause coverage, no cost.
- Atapattu, Domingo & Sutrisna: Poor planning and scheduling is among the three most critical cost factors for New Zealand transport projects; a perception ranking with no magnitude (abstract only).
- NZ Institute of Economic Research (NZIER), for BRANZ: Table 2 prints BRANZ inspection results of 12% for materials and 12% for construction methods (builders' opinion 7% and 14%); shares of defects as printed, and the model prices defects as a whole.
- New Zealand Infrastructure Commission / Te Waihanga: Discusses procurement and delivery capability as drivers of unit cost; benchmarking of unit costs, no share attributable to wrong quantities, sequencing or temporary works.
- New Zealand Infrastructure Commission / Te Waihanga: The builder not anticipating the consenting system is named as a contributor; no figure.
- SCIRT Learning Legacy: Describes the Christchurch rebuild procurement model and its $2.2 billion total; no planning, over-order or sequencing cost.