Research / Rework statistics / Contractor bore rework cost directly on 93% of projects; 23% of yearly profit lost

Contractor bore rework cost directly on 93% of projects; 23% of yearly profit lost

No figurepublished for this measure
AustraliaModerate confidenceContractor loss

Contractor bore rework cost directly on 93% of projects; 23% of yearly profit lost: no defensible figure has been published (Love, Ika, Ahiaga-Dagbui, Locatelli & Sing, 2019; Australia; moderate confidence).

What it is. Incidence and profit impact, not a share of contract value.

Sample. 98 projects with complete cost data (of 346 projects and 19,605 rework events), one contractor, six years of ledger data, public and private clients, building and infrastructure.

What it is not. Recorded rework was only 0.39% of contract value - the ledgers undercount. Margins were 6-9%, which is why 0.39% wiped out roughly a quarter of yearly profit. The 2018 paper on the same data reports 28%; cite one and say which.

Where it came from

rework/rework_contractor_bears_it · AU · F41, F42 ·the record ·link to this figure ·dispute this figure(or email support@demiton.io)