DEMITONMethodGitHub

Research / 2026 report

What the five diseases cost an Australian civil job, 2026

disease-economics by Demiton. Published 10 October 2026 from corpus release v5-17-g86fab48; each figure’s own page carries the current record.

On 115 Australian civil infrastructure projects, total rework averaged 10% of contract value (Love, Edwards, Watson and Davis 2010). Planned gross margin on Australian civil and transport work sits at about 9.9% (Love et al. 2017, with two later studies from the same group at 6% to 9%). If both numbers held on the same job, rework alone would take the whole margin. They come from different samples, so read that as the scale of the risk, not a measured result.

This record covers the five ways a contractor loses margin: rework, missed claims, disputes, cost drift and lapsed compliance. For each figure it gives the source, the sample, a confidence grade and what the figure does not measure. Every figure below is a current record; its page on research.demiton.io carries the calculation and the full caveat.

Rework

Figure Source and sample Grade What it does not measure
10% of contract value, total rework including indirect cost Love, Edwards, Watson & Davis 2010; questionnaire covering 115 Australian civil infrastructure projects Moderate Respondents’ estimates, not cost records
12.3% of contract value, 6.4% direct plus 5.9% indirect Love & Edwards 2005; national survey of 161 construction professionals, mixed sectors Moderate A perception survey; designers’ and project managers’ estimates differed significantly
Contractor bore the cost on 93% of projects; 23% of yearly profit lost Love, Ika, Ahiaga-Dagbui, Locatelli & Sing 2019; 98 projects with full cost data, one contractor, six years of ledgers Moderate Not a share of contract value. Recorded rework was only 0.39% of contract value, because ledgers undercount it

Missed claims

Figure Source and sample Grade What it does not measure
36.9% of the amount claimed sat in Queensland adjudications dismissed for no jurisdiction Adjudicate Today 2023; 246 published Queensland decisions, March 2022 to August 2023 Moderate A nominating authority’s own tally. Failure on procedure (timing, form), not merits; other routes to recovery may remain
10.6% of original contract value in client-approved change orders Love, Irani, Smith, Regan & Liu 2017; 67 public infrastructure projects, one contractor, 2011 to 2014 Moderate The size of the pot, not a loss. No study measures how much of it contractors fail to claim
9% of project cost in contract variations Queensland Audit Office 2022 (Report 16: 2021-22); the Queensland Government projects examined, mostly schools and public buildings Moderate A handful of audited building projects, not civil work. Money the client agreed to pay
AU$870 to AU$2,010 per working day of time-related site overhead on a $5M job (AU$17,400 to AU$40,300 over 20 wet days) O’Leary & Vaz-Serra 2025; 30 senior Australian estimators Low A worked example, not a measurement. One input is a UK 2002 figure read second-hand; the survey was mostly building work

Disputes

Figure Source and sample Grade What it does not measure
12% (NSW), 18% (Qld), 35% (Vic) of the amount claimed was determined in adjudication, 2018 to 2023 Liu (DGA Australia) 2023; state regulators’ statistics, 9,784 applications, 5,657 determinations Moderate The denominator includes the roughly 40% of applications that never reached a determination, so it understates recovery on decided disputes
50.9% of the amount claimed awarded once adjudicated, NSW 2011-12 NSW Department of Finance & Services 2012 (statistics by UNSW); 779 released determinations High One year, fourteen years old, decided disputes only. Not comparable with the 2018 to 2023 ratios
14.9% of the amount claimed awarded, Queensland 2020-21 to 2024-25 pooled; 8.6% to 45.6% by year QBCC annual reports; 983 released decisions Moderate Pooled dollars, so one A$634m claim in 2024-25 dominates
AU$288,000 lost per unpaid subcontractor, Queensland Special Joint Taskforce (Byrne) 2019; 146 submissions, mostly small contractors Moderate Self-reported and self-selected. A per-case figure, never multiplied by a contract value

Cost drift

Figure Source and sample Grade What it does not measure
7% loss at completion, a 16-point swing from a 9% tendered margin Ryan & Duffield 2017; 28 completed Australian megaprojects over A$500m, Tier 1 open-book data Moderate Megaprojects only, selected for risk. Not the loss on a typical civil job
23% mean overrun from contract award (median 12.3%) Love, Zhou, Edwards, Irani & Sing 2017; 16 rail projects, one contractor, mostly WA Moderate Mostly scope variations the owner paid, not contractor losses
24% over the first promised cost Terrill & Danks (Grattan Institute) 2016; 836 Australian transport projects of $20m or more, 2001 to 2016 Moderate The owner’s overrun, mostly before a contractor is signed. Median overrun is 0%

Lapsed compliance

Figure Source and sample Grade What it does not measure
AU$1,200 to AU$97,408 per accident borne by the employer, short absence to fatality Allison, Hon & Xia 2019; Safe Work Australia 2012-13 data plus three Tier 2 case studies Moderate Not independent of the Safe Work data; no average per accident. Penalties are separate
19% of the total cost of work-related injury falls on employers, premiums included Safe Work Australia 2015; national estimate, AU$61.8bn total, construction AU$5.84bn High Societal cost, not the contractor’s bill. Latest edition covers 2012-13

What the record cannot tell you yet

Method

Every figure is a current record in the disease-economics corpus (release v5-17-g86fab48); withdrawn records are excluded. Each record was read from its source on a recorded date and holds the value, the sample, the denominator, a confidence grade (high, moderate or low) and a caveat naming what it does not measure. Figures are estimates with stated confidence, not measurements of any one job. Only a share of contract value may be multiplied by a contract value; per-incident and per-day amounts stay in their own currency and price year. Any record can be disputed through the public repository, github.com/demitonapp/disease-economics.

How to cite

Data licensed CC BY 4.0. Credit “disease-economics by Demiton” with the figure’s URL, for example: disease-economics by Demiton, “Mean total rework cost, 115 Australian civil infrastructure projects”, https://research.demiton.io/rework/rework_total_civil_survey/ (release v5-17-g86fab48). Quoted passages remain their authors’.

Demiton watches a contractor’s own registers for these five, so the figures above become that job’s figures.